- A certificate of conformance (CoC) and a certificate of compliance are used interchangeably on most job shop purchase orders: a signed statement from the supplier that the shipment meets the order, usually with no test data.
- Material certs (mill test reports, EN 10204 type 3.1 inspection certificates) and certificates of analysis (CoA) carry actual test results for a specific heat, batch or lot, so you can check them against the spec. EN 10204 type 2.1 has no test results, and type 2.2 has results that are not from your lot.
- On receipt, check five things on every cert: heat or lot number, spec and revision, values within spec limits, a signature, and a link to your PO. AS9100D clause 8.4.2 expects a process for evaluating the data in supplier test reports.
- Each checked cert is then referenced on AS9102 Form 2, field 10 (certificate of conformance number), on the row for that material or special process.
Is a certificate of conformance the same as a certificate of compliance?
On a machine shop's purchase orders, a certificate of conformance and a certificate of compliance usually mean the same thing. Both are a statement from the supplier, signed by someone with authority, saying the shipment meets the purchase order. Customers use both names, sometimes in the same document.
Where people do draw a line, it runs like this: conformance means the product conforms to the drawing, specs and PO; compliance means it complies with a rule, a regulation or a program requirement (an environmental directive, an export rule, a contract clause). That distinction is real in some industries. The title on the document matters far less to an aerospace customer than what the document states.
What gets a CoC rejected is not saying what the customer's PO asked it to say. Read the quality clause. If the clause asks the certificate to state the material spec, the processor, or a counterfeit-parts statement, put those on it, whatever you title the document.
What certs does a job shop handle, and what does each one prove?
A job shop typically handles eight kinds of cert: CoCs, mill test reports, the four EN 10204 types, certificates of analysis and special-process certs. They differ in who issues them and whether they carry test results for the material you actually received.
| Document | Who issues it | What it proves | What to check on receipt |
|---|---|---|---|
| Certificate of conformance (CoC) / certificate of compliance | The supplier of the product or service: a distributor, a hardware supplier, a job shop to its customer | The supplier states the shipment meets the PO. A declaration, usually without test data. | Your PO number, part or material, quantity, lot. Signature and date. Any statement your PO required. |
| Mill test report (MTR) / mill cert | The mill that melted or produced the material (passed on by the distributor) | Chemistry and mechanical test results for a specific heat, against the named spec. | Heat number matches the bar tag. Spec and revision match the drawing. Every value inside spec limits. |
| EN 10204 type 2.1 (declaration of compliance with the order) | Manufacturer | Statement of compliance with the order. No test results. | Treat like a CoC. Not enough where the drawing, spec or PO wants test data. |
| EN 10204 type 2.2 (test report) | Manufacturer | Compliance with the order, plus test results from non-specific inspection (results for that product type, not necessarily your heat or lot). | Know that the numbers aren't from your heat. Usually not enough where the spec or PO wants results for the delivered lot. |
| EN 10204 type 3.1 (inspection certificate) | Manufacturer, validated by its authorized inspection representative, who is independent of the manufacturing department | Test results from specific inspection of the product actually delivered. | Heat or lot match. Spec and revision. Values within limits. The inspection representative's validation. |
| EN 10204 type 3.2 (inspection certificate) | Manufacturer's independent authorized inspection representative, plus either the purchaser's authorized representative or the inspector designated by official regulations | Same as 3.1, with a second, outside validation. | As 3.1, plus both validations present. Only needed if your customer or spec requires it. |
| Certificate of analysis (CoA) | The producer or a test lab | Actual test results for a specific batch or lot. Common for chemicals, resins and coatings; sometimes used loosely for metal test reports. | Lot number, the test methods named, results against the spec limits, the lab's signature. |
| Special-process cert (heat treat, plating, anodize, passivation, NDT) | The processor | The process was done to a named spec on your parts, often with test results (hardness, coating thickness). | Spec and revision, class or type, your PO and part number, quantity, results within limits, processor approval if your customer requires it. |
EN 10204 types are summarized from the 2004 edition (EN 10204:2004), which has four types: 2.1, 2.2, 3.1 and 3.2. If your customer's spec calls out a different cert type or edition, follow the spec.
What is the difference between a certificate of conformance and a certificate of analysis?
A certificate of conformance states that the product meets requirements, usually with no test data. A certificate of analysis reports measured test results for a specific batch or lot. The short way to say it: a CoC is a promise, a CoA is evidence.
A CoA, like an MTR, gives you numbers you can compare with the spec yourself. That difference matters under AS9100D clause 8.4.2 (type and extent of control). When you use a supplier's test reports to verify what you bought, AS9100D expects a process for evaluating the data in those reports, not just filing them. Where the customer or your shop has flagged raw material as a significant risk, the same clause also expects a process to validate the accuracy of test reports. Matching the cert to the PO isn't evaluating the data. Comparing the yield strength on the cert to the minimum in the spec is.
How do you check a material cert on receipt?
Check a material cert line by line against the drawing and the material spec: heat or lot, spec and revision, temper, chemistry, mechanicals, size and form, signature, traceability to your PO, and any customer flowdowns. Take a 6061-T6 bar from a distributor. You'll usually get the mill's test report and the distributor's own CoC. Check them together:
- Heat or lot number. The number on the cert matches the number stamped or tagged on the bar. If the distributor cut it, their paperwork should carry the heat through.
- Spec and revision. The cert names the material spec your drawing calls out, at a revision your customer accepts. A cert to a different spec isn't automatically a substitute.
- Condition or temper. T6 on the drawing, T6 on the cert. T651 or another variant? Check the drawing allows it.
- Chemistry. Every element reported is inside the spec range.
- Mechanicals. Tensile, yield and elongation at or above the spec minimums for that size and form.
- Size and form. Bar, plate or extrusion, in a size range the spec values apply to.
- Signature or validation. Someone with authority signed it.
- Traceability to your PO. The distributor's CoC ties the heat to your PO and line.
- Customer-specific requirements. Country of melt, approved mill, or other clauses your PO flows down.
Initial and date the cert when you've checked it, or record the check in your receiving system. That record is the evidence an auditor looks for under AS9100D 8.4. More on that in the AS9100 audit checklist for FAI records.
The material and process callouts on a drawing are where Form 2 starts. Balloon them with the rest.
Try the free balloonerHow do certs feed AS9102 Form 2?
Certs feed AS9102 Form 2 through one row per material, special process or functional test, with the cert's number in field 10. Form 2, product accountability, is where the certs land on a first article inspection report (FAIR). In the AS9102 Rev C layout, the fields that touch certs are:
| Form 2 field | Where it comes from |
|---|---|
| 5. Material or process name | The drawing callout: "Aluminum 6061-T6 bar", "Anodize, Type II, Class 2" |
| 6. Specification number | The spec named on the drawing, matched to the spec on the cert |
| 7. Code | Any code your customer requires for that material or process, per their instructions |
| 8. Special process supplier code | The processor's name or supplier code, often from your customer's approved list |
| 9. Customer approval verification | Yes, No or N/A: is that source approved by the customer where approval is required? |
| 10. Certificate of conformance number | The cert number from the mill, distributor or processor (for example a raw material test report number or a special-process cert number) |
Rev C removed the signature block from Form 2; the FAIR is signed on Form 1. Two habits make Form 2 painless. First, require certs with the shipment, on the PO to every processor and distributor, so you're not chasing them at FAI time. Second, check the cert at receiving, not at FAI. By the time the FAI is being assembled, the parts are made and a bad cert is a much bigger problem. The full field-by-field walk-through is in AS9102 Form 2 explained, and there's a free Form 2 Excel template; check its field layout against the form your customer requires.
What should a job shop's certificate of conformance include?
A job shop's CoC should name the customer PO and line, part number and revision, quantity and lot or serials, material spec and heat, special processes and their cert numbers, the FAI report, any deviations, a certification statement, and a dated signature. When you ship to your customer, your CoC is the document their receiving inspector checks. Make it easy. A sample, with fictional names:
CERTIFICATE OF CONFORMANCE No. C-24117
Example Machine Co., 100 Industrial Way, Anytown, USA
Customer: Example Aero Customer, Inc.
Customer PO: PO 55-01882, line 2
Part number: 4471-002 Rev: C Name: Housing, sensor
Quantity: 50 Lot: L2410-07 (S/N 001-050)
Material: Aluminum 6061-T6 bar, per [spec named on drawing]
Heat 7C2215, mill cert ref MTR-88213
Processes: Anodize Type II Class 2 per [spec named on drawing]
Processor: Example Finishing LLC, cert EF-30917
First article: FAI report FAI-4471-002-C, full, submitted 10/14
Deviations: None
We certify that the parts listed above were manufactured,
inspected and tested in accordance with the drawing, the
specifications named, and all requirements of the purchase
order, and that records are on file and available for review.
Signed: ____________ J. Smith, Quality Manager 10/29/2026
What makes it good:
- Every number traces. PO, part, revision, lot, heat, process certs, FAI report. Their inspector can check any of them against your records.
- Specs are named, not implied. "Per drawing" alone makes the receiver go look it up.
- Deviations are stated, even when there are none. If you shipped under an approved deviation, reference its number here.
- Someone with authority signs and dates it. Not a printed name with no signature.
- It carries whatever the PO required. If the PO asks for a specific statement, the statement is on the cert word for word.
Only certify what you have records for. A CoC is a signed statement. If an audit or a field failure pulls it later, the signature is yours.
Where does software help with certs?
Software helps keep each cert reference attached to the right FAI report; it can't make suppliers send certs on time or check the values for you. In Toolrick, Form 2 rows sit next to the ballooned drawing and Form 3, the cert references live with the FAI, and a preparer and a reviewer sign the report. You still check the values against the spec. Try the free ballooner on a drawing with material and finish callouts to see where Form 2 starts.
Related: AS9102 Form 2 explained · AS9100 audit checklist: FAI records · AS9102 Form 3 explained · Full vs partial FAI · DFARS compliant material
FAQ
Is a certificate of conformance the same as a certificate of compliance?
On most job shop purchase orders, yes. A certificate of conformance and a certificate of compliance are both a signed statement from the supplier that the shipment meets the order's requirements. Where people draw a line, conformance means meeting the drawing and specs, and compliance means meeting a rule or regulation. What matters is that the certificate states what your customer's PO asks it to state.
What is the difference between a certificate of conformance and a certificate of analysis?
A certificate of conformance is a supplier's statement that the product meets requirements, and it usually contains no test data. A certificate of analysis reports actual test results for a specific batch or lot. A CoC tells you the supplier says the product is right; a CoA or mill test report gives you numbers you can check against the spec yourself.
What is an EN 10204 3.1 material certificate?
An EN 10204 type 3.1 inspection certificate reports test results from specific inspection of the product actually delivered, validated by the manufacturer's authorized inspection representative, who is independent of the manufacturing department. Type 3.2 adds validation by the purchaser's authorized representative or an inspector designated by official regulations. Type 2.1 has no test results, and type 2.2 has results from non-specific inspection.
Is a material cert enough for AS9102 Form 2?
A material cert is the evidence for AS9102 Form 2, not the whole job. Form 2 lists each material, special process and functional test with its specification and a certificate number in field 10. Before you reference the cert, check that the heat or lot matches the material you used, that the spec and revision match the drawing, and that the reported values fall within the spec limits.
Sources
- EN 10204 certificate types, Wermac
- EN 10204 2.1 vs 2.2 vs 3.1 vs 3.2, Project Materials
- Certificate of Conformity (COC) guide, GoComet
- AS9100 8.4.2 Type and extent of control: external provider test reports, Elsmar Cove forum
- AS9102C Form 2 details, Paradygm
- AS9102 Rev C training (Form 2 signature removed), Paradygm
- FAIR Form 2, Net-Inspect Help Center