- First piece inspection approves a setup. The operator or inspector checks the features a setup controls, every time the job is set up, before the rest of the run continues. IATF 16949 calls this verification of job set-ups (clause 8.5.1.3).
- First article inspection approves the production process for a part number. Under AS9102, every characteristic on the drawing, plus materials, special processes and functional tests, is verified on a representative part from the first production run and recorded on Forms 1, 2 and 3.
- An FAI is redone only after a change. AS9102 triggers include a design change, a change of process, source, tooling, material, location or NC program, a disruptive event, or a two-year lapse in production.
- A first piece check can serve as the FAI only if it covers everything an FAI covers and is recorded like one. Eight dimensions on a setup sheet is not an FAI.
What is the difference between first article and first piece inspection?
First piece inspection proves a setup is right for one run. First article inspection proves the production process can make a part number to every requirement on the drawing, and that proof holds until something changes.
On the bench, the two checks look alike. A part comes off the machine, someone measures it, someone signs. The difference is what each check proves and how long the answer lasts.
First piece inspection (also called first-off, setup approval or setup verification) asks: is this setup right, today? The setter loads a program, touches off tools, runs one part, and the features that setup produces are checked before the rest of the lot runs. First piece inspection happens at every setup, at every shift change if your procedure says so, and after a tool break or offset change. The answer is good for that run.
First article inspection (FAI) asks: can our production process make this part number to every requirement on the drawing? Under AS9102, the aerospace FAI standard, that means a representative part from the first production run, every balloon on the drawing measured or verified, the material and special process certs accounted for on Form 2, and the report signed on Form 1. The answer holds until a design change; a change of process, inspection method, tooling, material, source, location or NC program that could affect fit, form or function; a natural or man-made event that could affect the process; or two years without production.
Put simply: first piece inspection is about the setup, first article inspection is about the part number. A job shop does dozens of first pieces for every FAI.
How do first piece, FAI, in-process, final, source and receiving inspection compare?
The six inspections differ by who does them and when: the supplier runs first piece, in-process and final inspection on every job, runs FAI once per part number and change, and the customer runs source and receiving inspection.
| Inspection | Who does it | When | What it proves | Record it leaves |
|---|---|---|---|---|
| First piece (setup approval) | Setter, operator or floor inspector | Every setup, and after tool, offset or program changes | The setup produces the features it controls within tolerance | Setup sheet or traveler sign-off with the checked dimensions |
| First article (FAI) | Quality, with a second person reviewing or approving where possible | New part number, and after the AS9102 trigger events | The production process makes a part meeting every design requirement | FAIR: Forms 1, 2 and 3, ballooned drawing, certs, CMM reports, NCRs |
| In-process | Operator or roving inspector | At set frequencies during the run, per the router or control plan | The process hasn't drifted | In-process check sheet, SPC chart, CMM sample reports |
| Final | Quality inspector | Before the lot is released to ship | The lot meets the order's acceptance requirements | Final inspection record, sampling record, C of C |
| Source | Customer quality rep, or a government rep (such as DCMA) on defense work | At the supplier's site, before shipment, when the PO calls for it | The customer has verified the product or witnessed the inspection before it leaves | Source inspection stamp or release on the shipping paperwork |
| Receiving (incoming) | The buyer's receiving inspection | When parts arrive at the buyer | The shipment matches the order: right part, revision, quantity, paperwork, no damage, sample dimensions | Receiving inspection record, accept or reject tag |
Three of the six inspections are the supplier's on every job (first piece, in-process, final). One is the supplier's once per part number and change (FAI). Two belong to the customer (source and receiving). A shop that buys outside processing also runs receiving inspection on its own suppliers.
How does calling a first piece check an "FAI" become an audit finding?
The finding comes when an auditor asks for the FAI record and gets a setup sheet. A setup check covers a few features; an AS9100 auditor expects every characteristic, the materials and special processes, and a signed report.
Here's how it plays out. A shop runs an aluminum housing for a new aerospace customer. The drawing carries 62 balloons once you count the notes. On the traveler, operation 10 has a box labelled "FAI". The setter runs one part and checks the eight features the first operation controls: two bores, a face-to-face, three hole positions and two depths. The inspector initials the box. Parts ship.
Eight months later an AS9100 auditor samples that part number and asks for the production process verification record. The shop produces the traveler. The auditor counts eight dimensions against a 62-characteristic drawing, finds no Form 2 accounting for the anodize and the material cert, and no signed Form 1. The finding writes itself: no evidence of production process verification (first article inspection) for a new part.
Nobody did anything dishonest. The traveler said "FAI", and everyone believed it. The label caused the finding.
Same clause number, different meaning. In AS9100D, clause 8.5.1.3 is production process verification, the clause behind first article inspection. In IATF 16949, clause 8.5.1.3 is verification of job set-ups, which covers first-off approval (and last-off comparison where applicable). Shops that hold both certificates, or hire inspectors from automotive, mix the two up easily.
Other versions of the same mistake
- FAI on a prototype. The FAI part was made on a different machine, with a different program, before the production process existed. AS9102 wants a representative part from the production process. A prototype layout is useful engineering data, not the FAI.
- FAI on every lot. Some shops do a full layout on every order "to be safe" and call each one an FAI. A full layout per lot costs inspection hours and muddies the record: an auditor will ask which one is the baseline for your next partial FAI.
- Receiving inspection as FAI. A shop that buys finished machined parts from a sub-tier checks a few dimensions at receiving and files the result as the FAI. The sub-tier's FAI, or your own full layout, is still owed.
- Source inspection as FAI. The customer's rep witnessed the inspection and stamped the paperwork. The stamp is the customer's verification. Your FAIR still needs your own preparer and approver on Form 1.
How do you keep first piece and FAI separate on the shop floor?
Give the two checks different names on the traveler, and let the FAI log, not the operator, decide when an FAI is due. These five steps cover it:
- Rename the traveler box. Use "Setup approval" or "First piece" for the per-setup check. Reserve "FAI" for the AS9102 record, and give the FAI its own operation.
- Let the system decide when an FAI is due. At order entry, check part number and drawing revision against your FAI log. New part, new revision, process change, or more than two years since the last production run: flag it before the job is released.
- Make the first production part the FAI part when one is due. Set up, approve the first piece, then run the FAI part with the production program, tooling and fixtures, and send it through the full layout and outside processing like the rest of the lot.
- Balloon the whole drawing, notes included. The FAI accounts for every characteristic. The ballooning guide covers what counts.
- File the FAIR where an auditor will look for it. File by part number and revision, with the baseline clearly marked, so the next partial FAI has something to reference.
If you're unsure whether a part has a real FAI on file, our first article inspection checklist lists what a complete package contains, and what auditors check in FAI records covers the audit side.
An FAI starts with every characteristic numbered, notes included. See how the free ballooner handles one of your drawings.
Try the free balloonerCan the first piece be the first article?
Yes, and often it should be. AS9102 doesn't require the FAI part to be the very first part off the machine, but it does require a representative part made by the production process.
In a job shop running a new part number, the first good part after setup approval is usually the most representative part you'll get. Mark it, keep it with the traveler, finish it through every operation including outside processes, and inspect it in full.
What the FAI can't be is the setup check with a new name. The test is simple: could a reviewer pick any balloon on the drawing and find its actual result in your record? If not, the record is a first piece check.
Frequently asked questions
Is first piece inspection the same as first article inspection?
No. First piece inspection approves a machine setup: it checks the features that setup controls and is repeated at every setup. First article inspection, under AS9102, verifies every characteristic on the drawing, plus materials, special processes and functional tests, on a representative part from the production process. An FAI is repeated only after a design, process, tooling, source or location change, or a two-year production lapse.
Can a first piece inspection count as an FAI?
Only if it actually is one. The record must cover every characteristic on the drawing, plus materials, special processes and functional tests, on AS9102 Forms 1, 2 and 3 or the customer's format. A first part measured in full can be the FAI if it was made with the production process, program and tooling. A setup check of a few features cannot.
What is the difference between first article inspection and receiving inspection?
First article inspection is done by the manufacturer to prove its production process makes a conforming part. Receiving (incoming) inspection is done by the buyer when parts arrive, to check the shipment matches the order: part, revision, quantity, paperwork, damage and sample dimensions. A buyer may review the supplier's FAIR during receiving, but receiving inspection does not replace the FAI.
What is source inspection?
Source inspection is verification by the customer, or by a government representative such as DCMA on defense work, at the supplier's facility before parts ship. Source inspection can include witnessing an FAI, but it is the customer's activity. The supplier still prepares and signs its own FAIR, and the source inspection stamp does not replace the supplier's Form 1 signatures.
What does IATF 16949 clause 8.5.1.3 require?
IATF 16949 clause 8.5.1.3, verification of job set-ups, requires automotive suppliers to verify each set-up, for example at an initial run, a material changeover or a job change, typically with first-off (and, where applicable, last-off) part checks, and to keep records. It is first piece approval. AS9100D uses the same clause number, 8.5.1.3, for production process verification, the basis of first article inspection.
Where software helps
The gap between a first piece check and an FAI is mostly the full characteristic list and the paperwork around it. Toolrick balloons the whole drawing, notes and GD&T frames included, flags balloons it's unsure about, and builds Forms 1, 2 and 3 following the AS9102 Rev C layout and field numbering. A preparer and an approver sign, each re-authenticating, and every edit is logged, so the record you hand an auditor is the FAI, not a setup sheet.
Related: AS9102 Form 3 explained · PPAP vs FAI · Why FAI reports get rejected · Free AS9102 templates
Sources
- FAI requirements in AS9100 Rev D, Advisera (clause 8.5.1.3, production process verification).
- Verify your production process with AS 9100, LRQA.
- IATF 16949 8.5.1.3 Verification of job set-ups, explained, Quality System Analysist blog.
- FAI_STD-001 First Article Inspection standard, Sonaca (AS9102 full and partial FAI triggers, as flowed down by primes).
- AS9102C Form 1 details, Paradygm.
- AS9102 First Article Inspection Report Rev B vs Rev C, Net-Inspect.